KCS Neches River Bridge Fender Replacement

Orion Engineering & Consulting led a Design/Build effort for a 100% design and construction of a fender system at the KCS railway bridge in Beaumont. The design featured robust steel assemblies with concrete-filled piles, ensuring resilience against a 2,000 kip impact load. We provided construction services, navigating site changes through effective communication with our Marine team.

PROJECT HIGHLIGHTS

  • Design/Build collaboration with our Marine team
  • 100% design services for KCS railway bridge fender replacement
  • Structural steel jacketed assembly with steel pipe pile foundations
  • Approx. 185lf length for each assembly
  • Fender system designed for a 2,000 kip concentrated impact load
  • 84” and 72” diameter piles in wing wall sections filled with concrete
  • Construction services: submittal and RFI reviews
  • Successful navigation of site condition changes
  • Ensured successful implementation of the replacement fender system.

Comprehensive Design Services

Orion Engineering & Consulting led a Design/Build effort for a 100% design and construction of a fender system at the KCS railway bridge in Beaumont. The design featured robust steel assemblies with concrete-filled piles, ensuring resilience against a 2,000 kip impact load. We provided construction services, navigating site changes through effective communication with our Marine team.

Beyond design contributions, our team actively participated in the construction phase by providing valuable services, including thorough submittal and request for information (RFI) reviews. Throughout the project, Orion encountered various site condition changes, highlighting the importance of effective communication between our Engineering & Consulting and Marine teams. This collaborative communication strategy proved instrumental in successfully navigating and implementing the necessary adjustments, ensuring the overall success of the replacement fender system project. The coordination between our groups exemplifies the critical role of clear communication in overcoming challenges and achieving project objectives.