skip to main content

Vigor Harbor Island Habitat Restoration

Orion played a crucial role in the NRD Habitat Restoration at Vigor Shipyard in Seattle. Our work included demolition of several structures, reconstructing a new pier section, new stormwater system installation, and creation of new intertidal habitat areas. The project showcased our commitment to environmental restoration and infrastructure development.

PROJECT HIGHLIGHTS

  • Demolition of piers, shipways, whirly cranes, and structures
  • Abatement and removal of an existing substation
  • Removed contaminated sediments for upland disposal
  • Dredging of clean sediment and riprap for new intertidal habitats
  • Placed new slope armoring, riprap with quarry spall bedding, and geogrid
  • Reconstructed a portion of an existing pier with new steel pile, cast-in-place concrete, and crane rails
  • Installed timber pinch piles to support underwater slopes beneath a building
  • Construction of a new stormwater system, including conveyance piping, catch basins, lift stations, and detention tanks
  • Upgrades to existing treatment system
  • Maintained an overall commitment to environmental restoration and infrastructure development

Balancing Restoration and Construction Challenges

The comprehensive scope of work on the NRD Habitat Restoration project at Vigor Shipyard in Seattle, Washington involved the demolition of various structures including piers, shipways, whirly cranes, and an existing substation. Following the demolition, our team meticulously addressed environmental concerns by removing contaminated sediments, allowing for their upland disposal. Clean sediment and riprap were dredged and repurposed onsite to create new intertidal habitat areas.

A critical aspect of the project involved the construction of protective measures for the newly formed slopes. Orion implemented new slope armoring, along with riprap featuring quarry spall bedding and geogrid to provide stability and longevity of the restored areas. Simultaneously, a segment of an existing pier was reconstructed utilizing new steel pile, cast-in-place concrete, and crane rails to meet the shipyard's future operational needs. Timber pinch piles were strategically driven to support underwater slopes in an area that has a building above it.

Orion successfully executed the installation of a new stormwater system. This comprehensive system included conveyance piping, catch basins, lift stations, and detention tanks as well as upgrades to an existing treatment system. This project emphasizes our commitment to responsible infrastructure development and ecological restoration.

Related projects