skip to main content

NASA Causeway Maintenance Of Traffic

Orion was enlisted by the Florida Department of Transportation to replace the existing 1964 bascule bridge over the Indian River, crucial for SpaceX and Blue Origin launches. Our Engineering & Consulting team collaborated with our Marine team to design alternate Maintenance of Traffic (MOT) phases, ensuring safe construction practices and minimizing downtime, especially during the critical construction of the eastbound bridge span.

PROJECT HIGHLIGHTS

  • Construction of two high-level fixed bridges over the Indian River
  • Replacement of the existing 1964 bascule bridge due to deficiencies
  • Critical thoroughfare for mission hardware and key corridor for SpaceX and Blue Origin
  • Design of alternate Maintenance of Traffic (MOT) phases
  • Optimization of construction process, reducing duration and enhancing safety
  • Utilization of a single 2250 crane from land for setting spans 1 through 5
  • Development of two additional MOT phases and revision of a key phase for eastbound bridge construction
  • Inclusion of additional temporary pavement and lane shift for both eastbound and westbound traffic
  • Maintenance of all four existing lanes during the construction of the new eastbound bridge span
  • Provide design and signed and sealed plans for review and approval
  • Collaboration with the original engineer of record, NASA, and Florida Department of Transportation (FDOT)

Innovation for SpaceX and Blue Origin's Key Route

The Florida Department of Transportation (FDOT) enlisted Orion to embark on a critical infrastructure project: the construction of two high-level fixed bridges spanning the Indian River. The existing bascule bridge, dating back to 1964, presented numerous deficiencies, compelling FDOT to seek its replacement for the safe and efficient transportation of freight and launch materials. Recognized as a crucial thoroughfare for essential mission hardware, the new bridges would serve as the primary corridor for commercial spaceflights undertaken by industry giants such as SpaceX and Blue Origin.

Our Marine group, in turn, engaged the expertise of our Engineering & Consulting group to address the intricate challenge of designing alternate Maintenance of Traffic (MOT) phases. This strategic planning aimed to facilitate our Marine team in setting spans 1 through 5 with a single 2250 crane from land. The primary objectives were to reduce construction duration and establish a safer work zone. We not only developed two additional MOT phases but also revised a key phase linked to the construction of the eastbound bridge structure.

The comprehensive design envisioned by our Engineering & Consulting team incorporated innovative elements, including the introduction of additional temporary pavement and a lane shift for both eastbound and westbound traffic. This strategic approach ensured that all four existing lanes could remain open throughout the construction of the new eastbound bridge span. Our dedicated staff went on to provide the design and meticulously crafted plans, which were then subjected to rigorous review and approval processes involving the original engineer of record, NASA, and FDOT. This collaborative effort aimed at meeting the highest standards and ensuring the successful realization of this ambitious bridge construction project.

Related projects